Reconstruction of Runway 9R-27L at Hartsfield Atlanta International Airport. The 33-Day Wonder – a Case History

January 1, 2002Technical Paper

 

D.S. Saxena
ASC geosciences, inc. USA

S.R. Kuchikulla
R&D Testing & Drilling, Inc. USA

D. Molloy
Hartsfield Atlanta International Airport USA

Frank O. Hayes
Aviation Consulting Engineers, Inc. USA

ABSTRACT. The William B. Hartsfield Atlanta International Airport (ATL) is the world’s busiest airport handling some 80 million passengers annually and serves major international and domestic markets around the globe. The airfield itself consists of roughly 4,200,000 sq m (5,000,000 sq yds) of pavement and includes 4 parallel runways measuring from 2,740 to 3,620 m (9,000 to 11,889 ft) long.

Runway 9R-27L was initially constructed over 27 years ago and has been in service  well beyond its design life. Due to pavement deterioration accelerated by alkali-silica reactivity (ASR) and other distress, the owner decided to remove Runway 9R-27L in late 1999 under a fast-track 36 day schedule. A joint venture of major contractors bid $ 52 million to complete the project under this fast track approach. A conventional approach was estimated to cost between $ 15 and $ 20 million without factoring the impact of a closed runway at some $ 475,000 per day over a normal 6 month construction timeframe.

Keywords: aviation, runways, PCI, ASR, quality control testing, flexural strength

Mr. Anupam Saxena, P.E., M. ASCE, is Technical Services Manager of ASC geosciences, inc., 2260 Godby Road, Atlanta, Georgia, 30349, USA

Mr. D.S. Saxena, P.E., F. ASCE, is Senior Principal and President of ASC geosciences, inc., 3055  Drane Field Road, Lakeland, Florida, 33813, USA

Mr. Subash Reddy Kuchikulla is Quality Assurance Engineer for ATL Geotechnical and Materials Programs at R&D Testing & Drilling, Inc., 2366 Sylvan Road SW, Atlanta, Georgia, 30344, USA

Mr. Daniel Molloy, P.E., is Assistant Aviation General Manager of Facilities at Hartsfield Atlanta International Airport, Department of Aviation, P.O. Box 20509, Atlanta, Georgia, 30320, USA

Mr. Frank O. Hayes is aviation pavement specialist with Aviation Consulting Engineers, Inc., 2400 Aviation Boulevard, Atlanta, Georgia, 30340, USA

BACKGROUND / FUTURE OF ATL 

The William B. Hartsfield Atlanta International Airport (ATL) is the world’s busiest airport handling over 80 million passengers annually and serves major international and domestic markets around the globe. ATL, owned by the City of Atlanta, is located on 1,518 ha (3,750 ac) located some 16 km (10 mi) south of downtown Atlanta. ATL is home to the largest airline hubbing operations in the world, Delta Air Lines, and its Central Passenger Terminal Complex (CPTC) is situated on 53 ha (130 ac) with approximately 529,500 sq m (5.7 million sq ft) of facilities including 6 concourses with 168 gates served by a central, underground airport people mover system and pedestrian mall. Currently, some 34 passenger airlines and 23 all-cargo airlines serve HAIA. The airfield itself consists of roughly 4,200,000 sq m (5,000,000 sq yds) of pavement and includes 4 parallel runways measuring from 2,740 to 3,620 m (9,000 to 11,889 ft) long. These east/west runways handle over 2,000 daily takeoffs and landings.

ATL has begun an intensive Capital Improvements Program totaling some $ 5.4 billion over the next 10 years. This CIP includes 4 major components: 1) a fifth runway; 2) an International Terminal; 3) a Consolidated Rental Car Facility; and, 4) a South Terminal.

ATL AIRFIELDS

History of Runways

In anticipation of considerable growth during the 1970s and 1980s, Runway 8R-26L was reconstructed in 1969 utilizing a 24/7 schedule over 40 days and nights. Construction was expedited in this fashion to reopen the runway as soon as possible. In 1972, 9R-27L was constructed, and in 1974 9L-27R was reconstructed. Runway 8L- 26R was constructed in 1984, with east and west extensions added to 9L-27R.

Throughout the 1980s and well into the 1990s, several pavement evaluation studies were conducted to look more closely at the performance of ATL airfield pavements and address concerns about their structural condition, pavement surface distress, concrete characteristic strengths, and age.

Pavement Evaluation Programs

1997 Pavement Evaluation

An exhaustive pavement evaluation program was performed in 1997 due to concerns about the relative age of some of the runways. The 1997 study employed several investigative techniques, including:

  • Falling Weight Deflectometer (FWD)
  • Visual Survey
  • Runway Ride Quality Measurement
  • Field Delamination Testing including Impact Echo Testing and Ground Penetrating Radar
  • Field Drilling and Sampling
  • Laboratory Testing including Petrographic Examination

Results of the 1997 study indicated the Pavement Condition Index (PCI) of the runways ranged from 53 to 97 with most values in excess of 70. The predominate distress observed was widespread map cracking in each of the runways. In Runway 9R-27L in particular, the joint distress was manifested into localized spall features which were increasing at an accelerating rate, as illustrated in Figure 1. It was noted that while the overall condition of Runway 8R-26L would appear lower than that of Runway 9R-27L, the results of PCI data indicate that 9R-27L was deteriorating at a faster rate than Runway 8R-26L, particularly with respect to the pavement keel or center section. Table 1 summarizes 1997 PCI Data for all ATL runways.

Table 1            Pavement Condition Index for ATL Runways, 1997

Pavement Condition Scale
Excellent 85-100
Very Good 70-84
Good 55-69
Fair 40-54
Poor 25-39
Very Poor 10-24
Failed 0-9
Runway PCI Rating Range of PCI Values Projected Year in Which PCI Becomes Critical (=50)
9R-27L Fair to very good 42 to 80 1999
8R-26L fair to good 42 to 79 2001
9L-27R Good to excellent 57 to 99 2003
8L-26R Very good to excellent 59 to 100 2010-2015

The 1997 pavement evaluation study concluded that a pavement exhibiting a PCI value below 70 would require significant maintenance and one below 50 would require major rehabilitation or replacement.

1 2

Figure 1  Typical Joint Distress

1999 PCI Survey

Amongst growing concerns about the condition of Runway 9R-27L, a pavement evaluation study was again performed utilizing a heavy weight deflectometer (HWD) in lieu of the FWD. Results of the 1999 study indicated PCI values ranging from 25 to 79 with the center or keel portions of the runway again exhibiting significantly lower values.

Section Sample Unit Left (L) Center (C) Right (R)
AB-Line CD-Line EF-Line
01 01 72 72 70
left section 02 76 67 62
03 74 57 61
04 79 46 58
Average 75 61 63
02 05 79 32 74
keel section 06 76 45 74
07 76 50 48
Average 77 42 65
03 08 64 53 63
right section 09 25 44 65
10 53 67 63
11 45 70 61
12 59 71 63
Average 49 61 63

Figure 2 illustrates chronological trends of PCI for center pavement sections of the ATL runways.

3

Deterioration from ASR

During both the 1997 Pavement Evaluation and 1999 PCI Survey, evidence of alkali- silica reactivity (ASR) was observed in concrete cores from all 4 runways, as illustrated in Figure 3. The reactions appeared most severe in Runways 9R-27L and 8R-26L.  Voids in the concrete matrix in these runways appeared nearly filled with the gel  product of ASR. Furthermore, horizontal cracks within the top 15 cm (6 in.) were observed in cores from Runway 9R-27L. The spalling and surface cracks observed in Runway 9R-27L were load-associated and eth distress appeared to have been accelerated as a result of ASR. It was further noted that the ASR appeared worse in concrete pavement using Portland cement and less severe in concrete using slag cement.

Together, these observations in Runway 9R-27L indicated ASR had in fact contributed to the deterioration of the concrete pavement to a point where replacement of the  runway was considered necessary.

4 5 6 7

RECONSTRUCTION OF RUNWAY 9R-27L

Overall Construction Approach

While replacement of Runway 9R-27L was conceptualized in early 1998, a typical reconstruction schedule of some 6 to 7 months was not acceptable because the runway handled one-fourth of the daily flight operations and was also only one of two CATIIIB certified runways that provided pilots with the best landing capability in severe weather. The project designer, Aviation Consulting Engineers, Inc. (ACE) in association with the Department of Aviation is credited with the planning, design, and construction management of the Runway 9R-27L Reconstruction Program. An unprecedented planning effort began over 18 months in advance of construction and included close coordination and consultation with the City of Atlanta, major airlines, and FAA.  A  joint venture of major contractors included APAC Ballenger, C.W. Matthews Contracting, Swing Construction, and Mitchell Construction. Together, this team was selected to remove and replace the 2,740-m by 46-m (9,000-ft by 150-ft) wide Runway 9R-27L, over 167,000 sq m (200,000 sq yd) of 400- to 560-mm (16- to 22-in.) thick concrete pavement in only 36 days.

During this period, normal operations would be transferred to Taxiway R, just south of Runway 9R-27L, that was readied to serve as a temporary runway during this period. This fast-track alternative approach was bid at $ 52 million. A conventional approach was estimated to cost between $ 15 to $ 20 million, without factoring the impact of a closed runway at some $ 475,000 per day over a normal 6 month construction time frame. So actually, the fast-track bid was significantly less expensive to the owner. Because time was so critical, penalties for not meeting the construction schedule ran as high as $ 200 per minute.

Removal of Existing Pavements

A critical phase of the construction project was the removal of some 21,150 concrete panels, each measuring 2.3 m by 3.7 m (7.5 ft by 12 ft) by 406 mm to 559 mm (16 to 22 in.) thick. A specialty contractor, Penhall Company, was chosen for this task based on their experience in California with removal of earthquake-damaged bridges and interstates following major California earthquakes. Penhall mobilized multiple teams of operators and equipment from across the country to complete the task. Once the  existing concrete slabs were cut, unique pavement removal buckets were utilized to carry away a maximum of three 9,150-kg (20,150-lb) panels onto each flat bed truck for transport to a 5.7-ha (14-ac) stockpile yard accommodating some 1,900,000 kN (213,000 tons) of panels stacked on top of one another, sometimes as high as 13 panels (refer to Figure 4).

8 9

Figure 4  Removal of Existing Pavements

Concrete Mix Design and Construction Operations

A total of 13 trial concrete mix design were formulated.  Flexural strength data from  this mix design phase indicated that a target 7-day strength of 4,130 kPa (600 psi) as well as a target 28-day strength of 4,480 kPa (650 psi) could easily be achieved.

The newly-constructed runway was designed to have an average thickness of 46 cm (18 in.) and a design life cycle of well over 20 years.

The resource needs for this project were significant, including: I) 1,200+ workers working 24 hours per day, 7 days per week at the height of construction ; 2) 200 to 300 truck loads of materials per day; iii) three on-site concrete batch plants (refer to Figure 5), plus an existing off-site commercial batch plant as backup, each capable of  producing as much as 7.7 cu m (10 cu yds) per min.

Phase I operations for the project focused on a temporary modification of an adjacent taxiway which would serve as a replacement runway during construction. This phase lasted 70 days and included procurement and mobilization. Phase II comprised the actual runway reconstruction for a planned 36 day timeframe. Phase III was scheduled for 30 days to convert the temporary runway back to a taxiway, to remove runway lighting and install taxiway lighting, convert runway striping to taxiway markings, and remove temporary exits.

10 11

Figure 5  Batching and Placement of Concrete

QUALITY CONTROL TESTING 

Quality Assurance testing for the owner and Quality Control testing for the contractor were performed during several key phases of construction, including subgrade preparation, installation of a soil-cement base, bituminous pavement placement and, of course, concrete pavement placement.

In accordance with FAA P-501 specifications, testing during construction included casting beams for flexural strength. Between QA and QC functions, over 2,000 beams were cast.  Target design flexural strengths were 4,130 kPa (600 psi) at 7 days and  4,480 kPa (650 psi) at 28 days when tested in accordance with ASTM C 78. Tables 3 and 4 summarize QC strength data.

Table 3  Summary of Quality Control Flexural Strength Data

Test at Days N, sample size Range kPa / psi Average kPa / psi S.D. kPa / psi
1 166 1,930 – 4,892 3,197 544
280 – 710 464 79
3 166 2,825 – 5,994 611 599
410 – 870 4,210 87
7 318 3,514 – 6,201 665 482
510 – 900 4,582 70
28 349 4,823 – 7,648 811 530
700 – 1,110 5,588 77

Table 4  Summary of Quality Control Splitting Tensile Strength Data

N, sample size Range kPa / psi Average kPa / psi S.D. kPa / psi
56 25,011 – 41,340 31,350 3,569
3,630 – 6,000 4,550 518

Results of the strength testing for flexural strength on beams indicated that the ultimate 28-day target compressive strength of 4,480 kPa (650 psi) was generally achieved between 3 days and 7 days.

ACKNOWLEDGEMENTS

The authors acknowledge the cooperation of the entire design and construction team which was essential to the success of the 9R-27L Reconstruction project. Planning, design, and construction management were performed by Aviation Consulting Engineers, Inc. (ACE) in association with the Department of Aviation on behalf of the owner, City of Atlanta. A plaque was placed on the completed runway project to recognize and honor Mr. Frank Hayes with ACE for over 25 years of engineering service at ATL.

The construction team was led by a joint venture of 4 firms, including APAC Ballenger,

C.W. Matthews Contracting, Swing Construction, and Mitchell Construction, all from Georgia, USA.

About

2MNEXT (Materials Managers and Engineers, Inc.) was established in 2010 in Atlanta, Georgia to provide engineering and inspection services in the areas of geotechnical, environmental, pavement management, materials engineering and testing, and special inspections.